Do You Need Council Approval to Renovate a Bathroom in NSW?
Usually not: a bathroom renovation can be exempt development under the NSW Codes SEPP, which means no planning or construction approval from a council or certifier, provided every development standard is met.
The NSW Planning Portal describes exempt development as work that does not need planning or construction approval from a council or private certifier. The Housing Industry Association’s explainer, are bathroom and kitchen renovations exempt development, says a renovation under section 2.51 of the Codes SEPP may include new cabinetry, new waterproofing, re-tiling and new fixtures and fittings, in houses and apartments alike. It also sets out what keeps the job exempt. The work must not:
- Change the configuration of the room, which includes moving, demolishing or building a wall, even if the wall is non-loadbearing.
- Affect the load bearing capacity of the building.
- Reduce the size of a window or door that the room needs for light or ventilation.
- Make a change, such as a penetration, to a fire resisting component, which matters in apartments and attached homes.
Can you move the toilet or shower without approval?
Moving fixtures within the same room can stay exempt, as long as no walls move and the structure is untouched.
HIA names baths, vanities and sinks as fixtures that can be relocated as exempt development. A toilet or shower move is judged on the same tests, but it also moves drainage under the floor, which is plumbing work that only a licensed plumber can do and which may need joists or a slab to be cut. That is where a quick look underneath before the layout is settled pays off.
What other rules apply to exempt bathroom work?
The general rules for all exempt work: meet the building code, avoid State Heritage Register land, and handle asbestos properly.
HIA notes that exempt work must meet the deemed-to-satisfy provisions of the Building Code of Australia. The Codes SEPP also rules out exempt work on land with an item on the State Heritage Register, and limits asbestos removal without a licensed removalist. The Planning Portal reminds owners that buildings constructed before 1990 may contain asbestos, which takes in many older Central Coast bathrooms with fibre-cement wall sheets.
When Does a Bathroom Renovation Need Council Approval?
A bathroom renovation needs approval when it changes the room itself: moving or removing a wall, combining a separate toilet with the bathroom, enlarging the room, adding a new window or touching the structure. That work goes through a complying development certificate (CDC) or a development application (DA).
Knocking out the wall between a bathroom and a separate toilet is one of the most common requests, and it takes the job out of the exemption straight away. The Planning Portal’s page on home renovation as complying development says some internal alterations to existing dwellings may be carried out as complying development, which is usually the quicker path. Where a wall is loadbearing, an engineer designs what replaces it, and our guide to removing a load-bearing wall explains that process.
What if the house is heritage listed?
Check with Central Coast Council first, because some work on heritage items or in conservation areas needs a DA.
The Council’s heritage advice page says a development application will be needed for some work on heritage items or in heritage conservation areas, and that a listing does not stop a building being modernised. The same rules apply to kitchens, as our guide to kitchen renovation council approval explains.
What Waterproofing Rules Apply to a Bathroom Renovation?
Every wet area must be protected by a waterproofing system that meets AS 3740 or Part 10.2 of the NCC Housing Provisions, whether or not the job needed approval. The waterproofing is the part of a bathroom you never see and the part that fails most expensively.
The National Construction Code says compliance with AS 3740 or Part 10.2 of the ABCB Housing Provisions satisfies its wet area requirement. Part 10.2 sets out the minimums, including:
- Shower floor: waterproof, including any hob or step-down.
- Shower walls: waterproof to not less than 1800 mm above the floor substrate, with wall junctions waterproof at least 40 mm either side.
- The rest of the floor: water resistant over concrete or fibre-cement, but waterproof over a timber-based floor, which is what many older Central Coast homes have.
- Bath or spa: waterproof to not less than 150 mm above the lip.
- Falls: floors graded to the waste at between 1:80 and 1:50, so water runs away instead of pooling.
- Open showers: a waterstop at least 1500 mm from the shower rose.
Does the exhaust fan matter?
Yes. A fan that vents into the roof space instead of outside is one of the most common reasons a new bathroom grows mould.
The NCC requires bathroom exhaust to discharge to outdoor air. Our guide to mould in a rental property covers the flow rates and why getting the fan right matters as much as the membrane.
Who Can Do a Bathroom Renovation in NSW?
A licensed contractor must do bathroom renovation work worth more than $5,000 in labour and materials, and waterproofing and plumbing are licensed trades in their own right. Exempt from approval does not mean exempt from licensing.
NSW’s page on general building work lists bathroom, kitchen or laundry renovations as work that needs a licence above that threshold. The kitchen, bathroom and laundry renovation licence class excludes work affecting any load bearing part of the building, and specialist work must be subcontracted to the right licence holder. NSW’s waterproofing work page says you must have a licence or certificate to do waterproofing, and plumbing needs a licence regardless of the cost of the job.
HIA adds that the Design and Building Practitioners Act generally does not apply to exempt bathroom renovations in a single dwelling. If the bathroom is in a unit, approval from the owners corporation comes first, as our guide to strata bathroom renovation approval explains.
So Do You Need Approval for Your Bathroom Renovation?
If the walls stay where they are, the structure is untouched and no window gets smaller, a bathroom renovation is usually exempt and needs no council approval. Moving a wall, joining the toilet to the bathroom or a heritage listing each brings in an approval step.
Settle the layout and the approval path before choosing tiles. A bathroom that works within its walls can start sooner and is simpler to build. One that needs a wall gone involves a certifier, possibly an engineer, and a longer lead time.
Williamson Builds renovates bathrooms across all of the Central Coast, with Newcastle and Sydney by arrangement for larger jobs, under builder’s licence 399743C with $10 million in public liability cover. This guide is general information for NSW and is not planning advice, so confirm the current rules for your address before work starts.