What Are the BAL 29 Decking Requirements in NSW?
At BAL 29, an open deck has to be built entirely from bushfire-resisting timber, supports and framing included, or from a suitable alternative to timber. That is the main step up from BAL 19, where only the boards are restricted.
The National Construction Code sets the base rule. Clause H7D4 in Part H7 of NCC 2022 Volume Two says that in a designated bushfire prone area, a house, or a deck associated with a house, meets the bushfire requirement if it is built in accordance with AS 3959 or the NASH Standard for steel framed construction in bushfire areas. NSW has its own variations on top, which is why the NSW Rural Fire Service guidance matters as much as the Code.
WoodSolutions, the timber industry’s technical body, summarises what AS 3959 means for timber decks in its guide to timber framed housing in bushfire-prone areas. For an open, unenclosed deck at BAL 29, it lists the supports, framing and decking materials as all bushfire-resisting timber. The RFS describes BAL 29 as high risk, particularly from embers, debris and heat, which is why the frame underneath is treated the same as the boards on top.
In practice that means three questions get answered before a BAL 29 deck is drawn, let alone priced:
- Is the block mapped as bush fire prone land?
- Is BAL 29 the level that applies where the deck will sit, or does it change across the site?
- Does the deck need approval, and if so, which pathway?
How do you check if your block is bush fire prone?
Search the address on the RFS online tool, then confirm it on the property’s planning certificate.
The RFS has a free bush fire prone land tool, and its guide to building on bush fire prone land says you can also check with your local council or your Section 10.7 planning certificate. The same guide says unenclosed decks need to be made of materials that are more resistant to ignition, depending on the BAL for your property. On the Central Coast the map often catches blocks that do not feel like bush blocks, such as a street backing onto a reserve or a gully.
What Does Each BAL Level Mean for a Timber Deck?
Each step up the BAL scale narrows what a deck can be built from, from ordinary construction at BAL-LOW to non-timber alternatives at BAL 40 and Flame Zone. BAL 29 is the highest level where an all-timber deck is still an option.
The RFS describes six levels. These are its words for the risk at each one, followed by what the WoodSolutions summary of AS 3959 says for an open, unenclosed deck:
- BAL-LOW: lowest risk from a potential fire. Materials and building methods as usual.
- BAL 12.5: risk is primarily from potential embers during a fire. Supports and framing as usual, decking in bushfire-resisting timber or a listed dense species.
- BAL 19: moderate risk, particularly from embers and burning debris. Same deck rules as BAL 12.5.
- BAL 29: high risk, particularly from embers, debris and heat. Supports, framing and decking all in bushfire-resisting timber.
- BAL 40: very high risk, likely to be impacted by embers, debris, heat and potentially flames. Suitable alternatives to timber.
- BAL-FZ (Flame Zone): extreme risk, directly exposed to the flames of a potential fire front. Suitable alternatives to timber.
What changes if the deck is enclosed underneath?
The frame rules relax, but the boards do not.
For a deck with an enclosed subfloor, the same WoodSolutions guide lists no special requirements for supports and framing at BAL 12.5 to 40, with the decking itself still in bushfire-resisting timber at BAL 29 and alternatives to timber at BAL 40 and Flame Zone. The material used to enclose the subfloor is treated like an external wall. Your designer or certifier works from AS 3959 itself, so treat this as the shape of the rules, not the clause.
Is merbau decking BAL 29?
Yes. Merbau, also sold as kwila, is one of the seven species WoodSolutions lists as bushfire-resisting timber.
The full list is blackbutt, kwila (merbau), red ironbark, river red gum, silvertop ash, spotted gum and turpentine. Spotted gum, blackbutt and merbau are already the hardwoods we build most decks from, which is good news. At BAL 29 the joists, bearers and posts have to be on that list too, not just the boards you see, and the supplier should be able to confirm the species in writing.
What type of decking is suitable for bushfire-prone areas?
Bushfire-resisting hardwood up to BAL 29, and tested non-timber products at BAL 40 and Flame Zone.
Composite and other manufactured boards are a different conversation. Some are tested for particular BALs and some are not, and the manufacturer’s own technical documents say which. If the paperwork does not name your BAL, the board should not be on your quote. Our guide to the materials Central Coast homes need covers how we choose products for exposure and bushfire level.
Why Does the 5 Metre Rule Send So Many Decks to a Certifier?
Because a deck on bush fire prone land can only be exempt from approval if anything within 5 m of the house is non-combustible, and a timber deck is not. So most timber decks close to a house on mapped land need complying development or a development application.
The NSW Planning Portal’s page on exempt balconies, decks and patios lists the conditions, and one of them reads: if it is located on bushfire prone land and is less than 5 metres from a house it needs to be constructed of non-combustible material. Add the usual exempt limits, such as a floor no more than 1 m above ground and an area no more than 25 m², and very few timber decks on mapped land qualify. Our guide to council approval for a deck or pergola on the Central Coast walks through the other conditions.
Timber is still on the table. Start with the approval path, because the approval is what fixes the BAL and therefore the materials.
Can you use complying development on any BAL?
No. The RFS says complying development is only available on BAL-LOW, 12.5, 19 and 29 land.
The RFS building guide says BAL-40 and Flame Zone are not allowed under the complying development pathway, so a deck there goes through a full development application. It also says only an accredited bushfire consultant or the local council can endorse the BAL for complying development.
Who works out the BAL on the Central Coast?
An accredited bushfire consultant, or Central Coast Council itself.
Council takes applications for a Bushfire Attack Level (BAL) risk assessment certificate under the State’s exempt and complying development codes. A consultant’s report can be worth having on a steep or complicated block, because the BAL can change across a single site depending on slope and distance to the vegetation.
Does Replacing an Old Deck Mean Meeting Today’s Bushfire Rules?
A new or rebuilt deck that needs approval is assessed against the rules that apply now, whatever the old deck was built to. A genuine repair is different, but it is still worth doing in the right timber.
Plenty of Central Coast decks were built before the current bushfire mapping and standards, so an old treated pine deck on BAL-29 land is common. The ABCB’s guide to how the NCC applies to common building features says the Code usually applies when new work is carried out or existing structures are altered as part of an approved project, and that it does not regulate everyday use, routine maintenance or minor repairs.
Where that line falls on a particular deck is a question for the certifier, not a guess. What we can say from the tools is this: if a deck has reached the point where the frame is rotten, the repair has become a rebuild, and a rebuild on mapped land should be scoped for the BAL. When we do replace boards or joists on a bush fire prone block, we use bushfire-resisting hardwood anyway, because it costs nothing in looks and it is the right material for the site. Our deck repairs page covers how we decide between repair and rebuild.
What if Your Block Is Both Coastal and Bush Fire Prone?
Then the deck has to meet two tests at once: timber that suits the BAL and fixings that survive the salt. Getting one right and the other wrong is the most common mistake we see on the Coast.
Headland and beachside suburbs often back onto reserves, so the same deck can face embers from one side and salt spray from the other. The hardwoods that pass the bushfire rule handle coastal weather well. The weak point is usually metal: brackets, bolts, screws and post supports that corrode long before the timber is tired. A bushfire-compliant deck that is rusting off its stirrups is not a safe deck.
This is also where a kit deck tends to come unstuck, because a kit is specified for an average block, not for a BAL and a salt band at the same address. Our comparison of a kit deck and a deck built on site goes into that in more detail.
So What Should You Build on a Bush Fire Prone Central Coast Block?
Find the BAL first, pick the approval path second, then choose a bushfire-resisting hardwood, or a tested alternative at the higher levels, with fixings rated for the salt.
At BAL-12.5 and 19, a well-built hardwood deck in spotted gum, blackbutt or merbau is usually straightforward. At BAL-29 the frame matters as much as the boards, so the whole substructure gets specified in bushfire-resisting timber. At BAL-40 and Flame Zone, timber is generally off the table for the deck itself and the design starts with the approved alternatives.
Williamson Builds designs and builds decks on site across all of the Central Coast, with Newcastle and Sydney by arrangement for larger jobs. The work is done under builder’s licence 399743C with $10 million public liability cover and our lifetime workmanship guarantee. This guide is general information for NSW, not a BAL assessment, so check the RFS and NSW Planning pages linked above for the current rules and have the BAL confirmed for your block.